Decentralized aspiration solution for ARNIO production

2025. Just a few years ago, the furniture manufacturer ARNIO LLC faced a problem familiar to many manufacturers: dust accumulated in the workshops, the air was heavy, and modern machines were operating at full capacity. This posed health risks to employees, increased the likelihood of accidents, and affected product quality. There was an urgent need for a solution that would not only comply with regulations but also help develop production.

Solution from Aton Service

The Aton Service team approached the task individually. Instead of a single centralized aspiration system, which was impossible due to limitations, we proposed a decentralized solution:

  • we divided the production into sections;
  • we installed an FA filter unit with an energy-saving node in each section;
  • we ensured the system’s operation in different load modes with cost optimization.

Technical characteristics
System capacity: 38,000 m³/hour

Stable operating conditions are ensured for more than 10 modern machines

Project implementation
The project had its own history: more than three years passed from the first discussions to the launch — the company grew, changed, and the decision became increasingly relevant. But when the customer made the final decision, it took only three months to implement the idea and get it up and running.

Results

The air in the workshops became clean, and working conditions became comfortable.
The equipment began to operate stably, without failures.
The company received a modern solution that supports its further development.

Key effect for the client

For ARNIO, this was a turning point: the investment in aspiration turned into an investment in people, quality, and the future of the company.

  • Advantages of Aton Service
  • Technological solutions,
  • speed of implementation after the decision was made,
  • individual approach to the client.

Last Projects

  • Numina: an aspiration system with storage and briquetting for MDF and particleboard

    2026. Aton Service has implemented an aspiration system for the storage and briquetting of MDF and particleboard at the Numina production facility in Moldova. More
  • Modern Expo

    The aspiration system at the Modern Expo production facility

    2026. Aton Service completed a project to install a state-of-the-art fume extraction system at the Modern Expo production facility in Lutsk. The technical solution is based on the FS-AS 4 filtering plant combined with an extraction hood, which ensures effective capture of contaminated air directly at the welding site, its purification, and subsequent return to […] More
  • аспірація в агропромисловост

    Aton Service made Agromash-Kalina’s welding areas safe and modern

    In early 2025, Agromash-Kalina LLC, based in the Vinnytsia region, was presented with a challenge. Welding operations in the metalworking facility were producing smoke, dust, and fine particles, creating an unsafe working environment that failed to meet sanitary standards. The goal was clear: improve air quality, ensure safety, and enhance workplace comfort without stopping production. […] More